No. Jenis Kegiatan Uraian
I Galian Tanah Upah 16,72 / 1 = 17 HOK
Vol = 0.4 x 0.4 x 54.5
= 8,72 m3
Gal. Saluran
Vol = 2 x 2 x 2
= 8 m3
Vol Tot = 16,72 m3
II Pas. Batu (1:8)
Vol = 0.3 x 0.5 x 54.5 Bahan
= 8,175 m3 Batu 1,2 x 8,175 = 10 m3
Pasir 0,76 x 8,175 = 6 m3
Semen 2,4 x 8,175 = 20 Zak
Upah
Tukang 0,36 x 8,175 = 3 HOK
Pekerja 2,7 x 8,175 = 22 HOK
Mandor 0,135 x 8,175 = 1 HOK
Pch Bt 10 / 2 = 5 HOK
III Beton (1:3:5) Bahan
Vol Pasir 3,23 x 0,68 = 2 m3
Sloof = 0.15 x 0.2 x 54.5 Semen 3,23 x 5,73 = 19 m3
= 1,635 m3 Split 3,23 x 1,04 = 3 m3
Kolom = 0.15 x 0.15 x 3 x 14 Besi Ø 10 161,5 x 4 / 11,5 = 56 btg
= 0,945 m3 Besi Ø 6 161,5 / 0,2 x 0,45 / 11,5 = 32 btg
Ringbalk = 0.1 x 0.1 x 41 Bendrat = 5 kg
= 0,41 m3 Papan Cor = 30 lbr
Sopi2 = 0.1 x 0.1 x 24 Besi Ø 10 Septictank = 7 btg
= 0,24 m3 Upah
Vol Tot = 3,23 m3 Pekerja 3,23 x 4,6 = 15 HOK
Tukang 3,23 x 0,35 = 1 HOK
Mandor 3,23 x 0,203 = 1 HOK
Langsir 5 / 2 = 3 HOK
T. Besi 3,23 x 4,86 = 16 HOK
T. Kayu 3,23 x 4,86 = 16 HOK
IV Pas. Bata (1:8) Bahan
Vol = 41 x 3 Bata 122,5 x 70 = 8575 bh
= 123 m2 Pasir 122,5 x 0,084 = 10 m3
Vol Sopi2 = 2.5 x 2 x 3 Semen 122,5 x 0,27 = 33 zak
= 15 m2
V. Tot = 138 m2 Upah
Vol Kusen Pekerja 122,5 x 0,525 = 64 HOK
= 15,5 m2 Tukang 122,5 x 0,175 = 21 HOK
Vol Tot = 122,5 m2 Mandor 122,5 x 0,0263 = 3 HOK
V Plester+Aci tbl 1.5 cm (1:8) Bahan
Vol = 122.5 x 2 Pasir 0,025 x 245 = 6 m3
= 245 m2 Semen 0,168 x 245 = 41 Zak
Upah
Tukang 0,165 x 245 = 40 HOK
Pekerja 0,33 x 245 = 81 HOK
Mandor 0,0165 x 245 = 4 HOK
VI Cat Dinding Bahan
Vol = 122.5 x 2 Cat 245 x 0,188 = 46 kg
= 245 m2 Plamir 245 x 0,11 27 kg
Amplas 245 x 0,1 25 lbr
Upah
Pekerja 245 x 0,03 = 7 HOK
Tukang 245 x 0,045 = 11 HOK
Cat Kayu Bahan
V. Kusen = 10,5 m2 Cat 33,9 x 0,35 = 12 kg
V. Jend = 2 m2 Meni 33,9 x 0,11 = 4 kg
V. Pintu = 4 m2 M. Cat 33,9 x 0,08 = 3 ltr
V Bofen = 4,5 m2 Amplas 33,9 x 0,05 = 2 lbr
V. Riplnk = 12,9 m2
V tot = 33,9 m2 Upah
Pekerja 33,9 x 0,24 = 8 HOK
Tukang 33,9 x 0,188 = 6 HOK
VII Atap Bahan
Vol Kuda2 & Gording A. Kuda2
= 1,2 m3 Kayu 8/12-3m = 7 btg
Vol Kaso & Reng Kayu 6/12-3m = 2 btg
= 1,6 m3 B. Gording
Vol Genteng Kayu 8/12-4m = 21
= 110 m2 Risplank 2/20-4m = 10 lbr
Vol Nok Kaso 5/7-4m = 40 btg
= 11,5 m' Kaso 5/7-3m = 80 btg
Vol Lsplnk Reng 2/3-2m = 300 btg
= 43 m' Paku = 25 kg
Upah Kuda2
Pekerja 1,2 x 5,2 = 6 HOK
Tukang 1,2 x 15,6 = 19 HOK
Upah Kaso & Reng
Pekerja 1,6 x 0,2 = 0 HOK
Tukang 1,6 x 0,2 = 0 HOK
Bahan
Genteng 110 x 25 = 2750 bh
Nok Gent 11,5 x 3 = 35 bh
Pasir 11,5 x 0,033 = 0,5 m3
Semen 11,5 x 0,35 = 4 zak
Upah pas. Genteng
Pekerja 110 x 0,16 = 18 HOK
Tukang 110 x 0,08 = 9 HOK
Upah Pas. Nok
Pekerja 11,5 x 0,3 = 3 HOK
Tukang 11,5 x 0,15 = 2 HOK
Upah Pas. Lsplnk
Pekerja 43 x 0,19 = 8 HOK
Tukang 43 x 0,52 = 22 HOK
VIII Lantai Bahan
Vol = 9.5 x 7 Keramik (30:30) = 66,5
= 66,5 m2 Pasir 66,5 x 0,018 = 1 m3
Semen 66,5 x 0,223 = 15 m3
Sirug 66,5 x 0,05 x 1,2 = 4 m3
Upah
Pekerja 66,5 x 0,274 = 18 HOK
Tukang 66,5 x 0,276 = 18 HOK
Mandor 66,5 x 0,0137 = 1 HOK
IX Plafon
Vol = 9.5 x 7 Bahan
= 66,5 m2 Eternit = 66,5 m2
Kayu 66,5 x 0,018 = 1,197 m3
Paku 5 x 1 = 5 kg
Upah
Pekerja 66,5 x 0,19 = 13 HOK
Tukang 66,5 x 0,52 = 35 HOK
Mandor 66,5 x 0,0137 = 1 HOK
Tidak ada komentar:
Posting Komentar