I Peng. Jalan (Sirtu) tebal 10 cm Bahan
Panjang = 960 m Sirtu 2400 x 0,1 x 1,2 = 288 m3
Lebar = 2,5 m
Volume = 2.400 m2 Upah
Pekerja Hampar Sirtu
288 / 4 = 72 HOK
II Perkerasan Jalan Telford Bahan
Tebal 10 cm Batu 500 x 0,1 x 1,2 = 60 m3
Panjang = 200 m Sirug 500 x 0,05 x 1,2 = 30 m3
Lebar = 2,5 m Sirtu 500 x 0,05 x 1,2 = 30 m3
Volume = 500 m3
Upah
Pecah Batu 60 / 2 = 30 HOK
Pasang Batu 500 / 4 = 125 HOK
Gelar Pasir & Sirtu 60 / 3 = 20 HOK