I Galian Tanah Upah 50,16 / 1 = 50 HOK
Vol = 0.4 x 0.4 x 54.5 x 3 kelas
= 26,16 m3
Gal. Saluran
Vol = 2 x 2 x 3
= 24 m3
Vol Tot = 50,16 m3
II Pas. Batu (1:8)
Vol = 0.3 x 0.5 x 54.5 x 3 Bahan
= 24,525 m3 Batu 1,2 x 24,525 = 29 m3
Pasir 0,76 x 24,525 = 19 m3
Semen 2,4 x 24,525 = 59 Zak
Upah
Tukang 0,36 x 24,525 = 9 HOK
Pekerja 2,7 x 24,525 = 66 HOK
Mandor 0,135 x 24,525 = 3 HOK
Pch Bt 29 / 2 = 15 HOK
III Beton (1:3:5) Bahan
Vol Pasir 9,69 x 0,68 = 7 m3
Sloof = 0.15 x 0.2 x 54.5x3 Semen 9,69 x 5,73 = 56 m3
= 4,905 m3 Split 9,69 x 1,04 = 10 m3
Kolom = 0.15 x 0.15 x 3 x 14 x 3 Besi Ø 10 161,5 x 4 / 11,5 = 56
= 2,835 m3 Besi Ø 6 161,5 / 0,2 x 0,45 / 11,5
Ringbalk = 0.1 x 0.1 x 41 x 3 Bendrat = 5 kg
= 1,23 m3 Papan Cor = 30 lbr
Sopi2 = 0.1 x 0.1 x 24 x 3 Besi Ø 10 Septictank = 7 btg
= 0,72 m3 Upah
Vol Tot = 9,69 m3 Pekerja 9,69 x 4,6 = 45 HOK
Tukang 9,69 x 0,35 = 3 HOK
Mandor 9,69 x 0,203 = 2 HOK
Langsir 17 / 2 = 9 HOK
T. Besi 9,69 x 4,86 = 47 HOK
T. Kayu 9,69 x 4,86 = 47 HOK
IV Pas. Bata (1:8) Bahan
Vol = 41 x 3 x 3 Bata 398,5 x 70 = 27895 bh
= 369 m2 Pasir 398,5 x 0,084 = 33 m3
Vol Sopi2 = 2.5 x 2 x 3 x 3 Semen 398,5 x 0,27 = 108 zak
= 45 m2
V. Tot = 414 m2 Upah
Vol Kusen Pekerja 398,5 x 0,525 = 209 HOK
= 15,5 m2 Tukang 398,5 x 0,175 = 70 HOK
Vol Tot = 398,5 m2 Mandor 398,5 x 0,0263 = 10 HOK
V Plester+Aci tbl 1.5 cm (1:8) Bahan
Vol = 122.5 x 2 x 3 Pasir 0,025 x 735 = 18 m3
= 735 m2 Semen 0,168 x 735 = 123 Zak
Upah
Tukang 0,165 x 735 = 121 HOK
Pekerja 0,33 x 735 = 243 HOK
Mandor 0,0165 x 735 = 12 HOK
VI Cat Dinding Bahan
Vol = 122.5 x 2 x 3 Cat 735 x 0,188 = 138 kg
= 735 m2 Plamir 735 x 0,11 81 kg
Amplas 735 x 0,1 74 lbr
Upah
Pekerja 735 x 0,03 = 22 HOK
Tukang 735 x 0,045 = 33 HOK
Cat Kayu Bahan
V. Kusen = 31,5 m2 Cat 101,7 x 0,35 = 36 kg
V. Jend = 6 m2 Meni 101,7 x 0,11 = 11 kg
V. Pintu = 12 m2 M. Cat 101,7 x 0,08 = 8 ltr
V Bofen = 13,5 m2 Amplas 101,7 x 0,05 = 5 lbr
V. Riplnk = 38,7 m2
V tot = 101,7 m2 Upah
Pekerja 101,7 x 0,24 = 24 HOK
Tukang 101,7 x 0,188 = 19 HOK
VII Atap Bahan
Vol Kuda2 & Gording A. Kuda2
= 3,6 m3 Kayu 8/12-3m = 21 btg
Vol Kaso & Reng Kayu 6/12-3m = 6 btg
= 4,8 m3 B. Gording
Vol Genteng Kayu 8/12-4m = 63
= 330 m2 Risplank 2/20-4m = 30 lbr
Vol Nok Kaso 5/7-4m = 120 btg
= 34,5 m' Kaso 5/7-3m = 240 btg
Vol Lsplnk Reng 2/3-2m = 900 btg
= 129 m' Paku = 75 kg
Upah Kuda2
Pekerja 3,6 x 5,2 = 24 HOK
Tukang 3,6 x 15,6 = 74 HOK
Upah Kaso & Reng
Pekerja 4,8 x 0,2 = 2 HOK
Tukang 4,8 x 0,2 = 2 HOK
Bahan
Genteng 330 x 25 = 8250 bh
Nok Gent 34,5 x 3 = 104 bh
Pasir 34,5 x 0,033 = 0,5 m3
Semen 34,5 x 0,35 = 12 zak
Upah pas. Genteng
Pekerja 330 x 0,16 = 53 HOK
Tukang 330 x 0,08 = 26 HOK
Upah Pas. Nok
Pekerja 34,5 x 0,3 = 10 HOK
Tukang 34,5 x 0,15 = 5 HOK
Upah Pas. Lsplnk
Pekerja 129 x 0,19 = 25 HOK
Tukang 129 x 0,52 = 67 HOK
VIII Lantai Bahan
Vol = 9.5 x 7 x3 Keramik (30:30) = 199,5
= 199,5 m2 Pasir 199,5 x 0,018 = 4 m3
Semen 199,5 x 0,223 = 44 m3
Sirug 199,5 x 0,05 x 1,2 = 12
Upah
Pekerja 199,5 x 0,274 = 55 HOK
Tukang 199,5 x 0,276 = 55 HOK
Mandor 199,5 x 0,0137 = 3 HOK
IX Plafon
Vol = 9.5 x 7 x 3 Bahan
= 199,5 m2 Eternit = 199,5 m2
Kayu 199,5 x 0,018 = 3,591 m3
Paku 5 x 1 = 5 kg
Upah
Pekerja 199,5 x 0,19 = 38 HOK
Tukang 199,5 x 0,52 = 104 HOK
Mandor 199,5 x 0,0137 = 3 HOK