No. Jenis Kegiatan Uraian
I Galian Upah
Panjang = 400 m Pekerja 0,8 x 70 = 56 HOK
Lebar = 0,35 m Mandor 0,027 x 70 = 2 HOK
Tinggi = 0,5 m
Volume = 70 m3
II Pasangan Batu (1:8) Bahan
Panjang = 300 m Batu 1,2 x 45 = 54 m3
Lebar = 0,3 m Pasir 0,76 x 45 = 34 m3
Tinggi = 0,5 m Semen 2,4 x 45 = 108 Zak
Volume = 45 m3
Upah
Tukang 0,36 x 45 = 16 HOK
Pekerja 2,7 x 45 = 122 HOK
Mandor 0,135 x 45 = 6 HOK
Pch Bt 54 / 2 = 27 HOK
Pasangan Batu (1:8) Bahan
Panjang = 100 m Batu 1,2 x 52,5 = 63 m3
Lebar = 0,35 m Pasir 0,76 x 52,5 = 40 m3
Tinggi = 1,5 m Semen 2,4 x 52,5 = 126 Zak
Volume = 52,5 m3
Upah
Tukang 0,36 x 52,5 = 19 HOK
Pekerja 2,7 x 52,5 = 142 HOK
Mandor 0,135 x 52,5 = 7 HOK
Plester + Aci T=1,5 (1:8) Bahan
Panjang = 400 m Pasir 0,025 x 140 = 4 m3
Lebar = 0,35 m Semen 0,168 x 140 = 24 Zak
Volume = 140 m2
Upah
Tukang 0,165 x 140 = 23 HOK
Pekerja 0,33 x 140 = 46 HOK
Mandor 0,0165 x 140 = 2 HOK
III Terucuk Bambu
Vol = 400 / 0.5 Bahan
= 800 bh Bambu 800 x 4 = 200 bh
Upah
Pekerja 800 / 15 = 53 HOK
Tidak ada komentar:
Posting Komentar